May 21-24 – street sweeping

June 3 - 7 – street sign replacement project

June 8 – Community garage sale

June – Playground maintenance – adding Playsoft mulch and rake; tighten parts; replace fences at playground and basketball court; weed and crack

Mid June to Late June – Wildfire Mitigation work on district open space/greenbelt

June – Sewer line inspection and cleaning

June 24-25 – Road patching/ crack filling on Aspen Drive and other streets in subdivision

July 22-26 - Major road project on Michael Way – mill and overlay